Singapore - QXY Staff Apartment Project
Residential Concrete Construction Interior Decoration
Return to List

Project Background


August 16, 2024, Singapore QXY Staff Apartment Project – Construction Demonstration of Putty Application, Putty Grinding, Indoor Coating Robot and Measuring Robot.
The apartment floors have been leveled. Partition boards are adopted for wall construction with good flatness; only simple surface treatment is required prior to spraying work. Severe honeycombing and pitting defects exist on concrete beams and columns.
Construction room dimensions: 7.3m × 6.6m (floor area 48.18 sq.m); ceiling height: 2.75m


Advantage of Robotics


Robot operation duration:Wall putty spraying: 20 minutesGrinding of putty-coated walls: 33 minutesWall latex paint spraying: 14 minutes

Upon completion of the construction works, the main contractor of QXY recognized the construction efficiency and finished quality delivered by the robotic equipment, spoke highly of the solution, and expressed intention for further cooperation in subsequent projects.



Deducting Door Opening
ProductWall AreaCoverage RateTime (min)Efficiency (m²/min)Efficiency (m²/hr)
Putty Application69.308495%203.3197.53
Putty Sanding69.308480%331.7100.81
Interior Spray Painting69.3084100%145297.04

Not Deducting Door Opening
ProductWall AreaCoverage RateTime (min)Efficiency (㎡/min)Efficiency (㎡/hr)
Putty Application75.308495%203.6214.63
Putty Sanding75.308480%331.8109.54
Interior Spray Painting75.3084100%145.4322.75